> Crews are installing ground anchors into the large slope between the railroad tracks and the Cyprus Shore community to prevent the slope from pushing the tracks further toward the coast. Two rows of ground anchors – 104 in row one and 116 in row two – are being drilled into bedrock deep beneath the slope.
>
> Contractors reached an important milestone in January 2023. The first row of 104 anchors has been installed and secured. Crews began excavation activities for row two in mid-January, and work is expected to continue through late March.